- Location: Gottlieb-Daimler-Str., Building 74
- Key figures:
- Length: 66 m, Width: 50 m
- Floors: 3
- Net floor area: 6,470 m2
- Usable area: 3,266 m2
- Total costs: 52.030 Mio. € (Construction costs: 40.900 Mio. €, Initial setup costs: 2.442 Mio. €, Major research instrumentations: 8.688 Mio. €)
- Construction time: 2020 - 2023
- Office space for 85 people
- Interdisciplinary research with teams from mechanical engineering, process engineering, physics, and computer science
- Laboratory units: Research takes place in three laboratory units. Each of these three units is equipped with major research instrumentations:
- Laboratory unit Ultra-Precision & Micro Manufacturing (UPMM)
- Laboratory unit Characterization & Measurement (CM)
- Laboratory unit Visualization & Scientific Computing (VSC)